Hollywood solar starts at the county, not on your roof

Written by the Solar Learning Lab research deskUpdated August 30, 202612 min read

Two documents explain most of what makes a Hollywood solar project go smoothly or badly. The first is Resolution R-2025-363, adopted October 9, 2025, which sets the city's photovoltaic permit at a flat $160, second review included free. The second is the High-Velocity Hurricane Zone chapter of Florida's building code, which is why your drawing set needs sealed engineering built for 170 mph design winds before anyone touches a rafter. Between those two sits a routing quirk unique to this corner of Broward County: plans go to the county first through ePermits OneStop, then to the city for plan review.

None of this is a reason to skip solar in Hollywood. It is a reason to hire someone who has run this exact gauntlet before, because the sequence is unforgiving of improvisation and completely manageable with the checklist in hand. We lay out the whole path below, each step with its source.

Know the flow before the first sales pitch

Ten minutes with the estimator and this page beats an hour with a rep who has never filed in Hollywood.

Estimate a Hollywood roof

One line on a fee schedule does a lot of work

The city's Comprehensive Schedule of Fees, adopted by Resolution R-2025-363 and effective immediately on adoption, prices a Photovoltaic System permit, solar panels with stationary energy storage included, at $160 flat. The second plan review costs nothing, and every review after the second bills at $40 per 15 minutes. Contrast that with the general building formula in the same resolution: a $100 minimum on work up to $1,000, then 10.00 percent of the first $1,000, 2.20 percent up to $1 million, and tighter percentages above. On a typical rooftop array, the flat PV line saves real money versus valuation pricing, and the reviewer-time meter after review two is a built-in penalty for sloppy submittals. A contractor who gets it right by the second pass costs you $160. One who needs a fourth pass is spending your money at $40 per quarter hour.

County first, city second, and a portal migration in the middle

Hollywood's routing is genuinely different from its neighbors. Per the city's ePermits OneStop page, a joint City of Hollywood and Broward County website lets applicants submit plans for Broward County approvals before submitting to the City of Hollywood for permitting plan review. Two gates, in order. Meanwhile the city side is mid-migration: Hollywood is launching the Accela Civic Application in phases, covering permit applications, review status tracking, contractor registration, inspection scheduling, and status checks around the clock, with contractor registration having opened Monday, August 12. Until the dust settles, the working assumption should be that your installer confirms the current filing path the week of submission, not from memory.

The human fallback still exists. The ePermits counter is Room 320 at City Hall, 2600 Hollywood Blvd, open Monday through Thursday, 7 a.m. to 6 p.m., reachable at 954.921.3335 and epermits@hollywoodfl.org, with plan reviewer questions handled through the QLESS call back appointment feature. The city publishes no fixed residential solar review timeline on the pages we fetched, so we quote none. Distrust anyone who does without a source.

Who is allowed to pull the permit is a two contractor question

Hollywood's Solar Photovoltaic System Checklist encodes a licensing structure that surprises buyers from anywhere else. If an electrical contractor holding an EC license pulls the solar permit, a roofing contractor with a CCC license must pull a separate structural sub permit for the panel attachment. The one-contractor path exists only for a solar contractor holding a CVC license, who can pull the permit without a roofing sub, but still needs an EC licensed electrical contractor on the job. Either way, two licenses touch your roof.

Use that as a bid filter. Ask each company which license pulls the main permit and who handles the structural attachment sub permit. A clean answer takes ten seconds. A muddled one predicts the change orders. The rest of the required package, per the same checklist: the Broward County Uniform Permit Application from a licensed electrical or solar contractor, a scale roof plan with panel locations, an electrical diagram covering array configuration, wiring, overcurrent protection, the inverter disconnect, grounding, and the AC connection, plus spec sheets and installation manuals for every component.

The paperwork that proves your array survives 170 mph

All of Hollywood sits in Broward County, which the Florida Building Commission places inside the High-Velocity Hurricane Zone. The HVHZ wind load tables in Florida Building Code Section 1620.2 run 156, 170, 180, and 185 mph across the four risk categories for the county set that includes Broward, and the ASCE 7-16 fact sheet from that commission names Broward for the 185 mph Risk Category IV figure. A typical home is Risk Category II, which means the racking and attachment math on your drawings is being checked against a 170 mph 3 second gust, at Exposure C or D, with rooftop equipment loads following ASCE 7 Chapter 29.

That is why two Hollywood submittal items exist that inland Florida buyers never see. Every drawing set must carry either a Florida Solar Energy Center System Approval Report or signed and sealed engineered drawings. And Broward layers on the Mandatory Countywide Rooftop Mounted Equipment Affidavit under Board Policy 22-03, required with the city checklist. Read this as a feature. The engineering burden that slows a careless bid is the same one that keeps arrays attached when a real storm arrives, and it is the main reason attachment hardware and racking specs deserve more scrutiny in your quote than the panel brand does.

FPL nets monthly, banks for a year, then pays wholesale

Florida's net metering baseline comes from Statute 366.91, and the operating rules live in Rule 25-6.065. The cycle works like this: the utility installs two-way metering at no additional cost, excess generation in any billing cycle becomes a kWh credit against the next month, and those credits can stack for as long as twelve months. When the calendar year closes, the leftover balance converts to cash at an average annual rate keyed to the COG-1 as available energy tariff, a wholesale figure well below retail. The design lesson is the same one the rule quietly teaches everywhere in Florida: size near your actual consumption. Overbuild and your surplus eventually converts at the cheap rate.

The friendly parts deserve equal billing. A typical Hollywood rooftop lands in Tier 1, 10 kW or less, and the rule forbids charging Tier 1 customers any fee, application fees included, that retail customers without self generation do not pay. Requiring liability insurance at Tier 1 is off the table too. The rule also sets clocks the utility must honor: a completeness response within 10 business days, an executed interconnection agreement within 30 calendar days of a complete application, and at least 10 days customer notice before first energizing. Two sizing constraints to know on paper: gross power rating may not exceed 90 percent of your distribution service rating, and inverter systems count AC nameplate as DC nameplate times 0.85. FPL itself is enormous, roughly 11 million people served across 35 counties, with Broward generating sites including the Dania Beach Clean Energy Center next door, per the Ten Year Site Plan.

Florida's remaining levers after the federal credit ended

The federal picture first, because it changed the math for every 2026 buyer: P.L. 119-21 repealed the Section 25D homeowner credit for expenditures after December 31, 2025, and since the tax code treats an expenditure as made when installation is completed, a system finished in 2026 gets nothing, per the Congressional Research Service. Carryforwards from earlier expenditures survive indefinitely.

What Florida still offers is unglamorous and durable. Under Statute 212.08(7)(hh), a solar energy system or any component of one carries no Florida sales tax, and the Florida Solar Energy Center certifies the qualifying hardware list to the state. Statute 193.624 tells the appraiser to disregard whatever value the equipment adds when assessing a residential property, covering collectors, photovoltaic modules, and inverters plus wiring and structural supports, for installations on or after January 1, 2013, with the 2017 amendments running through December 31, 2037. There is no Florida income tax credit and no statewide rebate that we could verify on the PSC's renewable energy pages. So the honest Hollywood case is bill offset at retail, tax-free equipment, an untouched assessment, and, paired with storage, a house that keeps some lights on when the grid does not.

Coastal output, modeled without the brochure gloss

Our downtown Hollywood run models 1578.4 kWh per year per installed kW, and the shape of the curve matters more than the total. March leads at 153.2 kWh per kW while July manages only 128.4, because early summer convection and cloud buildup take a real bite out of the season national calculators assume is peak. June, at 121.5, models below both January and February.

Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec

March models 153.2 kWh per kW, the annual peak. Summer cloud buildup pulls June down to 121.5, below several winter months, a coastal South Florida pattern worth pricing in.

PVGIS v5.2 model run by Solar Learning Lab on August 30, 2026, NSRDB radiation database. Fixed south facing mount, 30 degree tilt, 14 percent losses, downtown Hollywood coordinates. Your roof will differ. Model documentation lives at PVGIS. Hollywood's geography frames the market: 153,067 residents at the 2020 census on 30.78 square miles of southeastern Broward, with about 5 to 6 miles of Atlantic beachfront, per the city profile. Salt air is a maintenance variable on coastal blocks; ask what corrosion rating your racking carries.

The FPL price check

FPL averaged 13.71 cents per kWh across 5,236,277 residential customers in 2024, per EIA Table 6. FPL's own site blocks automated retrieval, so we quote the federal dataset rather than paraphrasing rate schedules we cannot fetch, and you should pull your actual bill for anything beyond planning math.

Energy sourceTypeAverage priceWhat that means
Florida Power & Light2024 residential average13.71¢ per kWhEIA Table 6, 2024 Utility Bundled Retail Sales, Residential.
Hollywood permit deskPhotovoltaic system permit, adopted October 9, 2025$160 flat, storage includedSecond review free, then $40 per 15 minutes per Resolution R-2025-363.
Hollywood rooftopPVGIS modeled output1578.4 kWh per kW annuallyFixed south facing model at 30 degree tilt. Individual roofs differ.

Price context from EIA Table 6; permit pricing from the city fee resolution. Year end credit balances settle at the COG-1 as available rate, not retail.

Crews working Broward roofs

The list includes shops based in Hollywood itself and nearby. Our two screening questions for this market: which license class pulls your permit here, and who produces the sealed HVHZ engineering. Companies that work this county weekly answer both without checking.

Ratings snapshot: Google Maps, August 2026, via the DataForSEO SERP feed. Zero companies paid us and none are endorsed by us.

Florida Electric & Solar logo

Florida Electric & Solar

North Miami, FL

5.0(76 Google reviews)

Sun Electronics

Miami Gardens, FL

4.6(54 Google reviews)

Solar Prime Usa logo

Solar Prime Usa

Hollywood, FL

4.9(45 Google reviews)

Solar Champs LLC

Hollywood, FL

4.4(38 Google reviews)

Smart Planet Solar - Solar Panel Installer

Fort Lauderdale, FL

5.0(15 Google reviews)

Ratings and review counts are Google Maps ratings for Hollywood local results, retrieved August 17, 2026 via the DataForSEO SERP API. We list the highest rated established companies we found. No company paid to appear here, and appearing here is not an endorsement. Check current reviews and licensing before you sign anything.

Run the estimate, then subtract the folklore

The calculator uses the 13.71 cent FPL average and our Hollywood production run. It does not model the twelve month credit cycle or the COG-1 true up, so a system sized far past your usage will look better in the tool than on your bill. Size near consumption and the tool is a fair screen.

$156
1,578

Slider top is our downtown Hollywood PVGIS run at 1,578.4 kWh per kW. Slider bottom trims 15 percent for shade and orientation. Summer cloud buildup makes March, not July, the strongest modeled month here.

$2.17

Cash quotes in Hollywood cluster near $2.17 per watt, against a $3.50 national 2024 median (LBNL). Use your quote.

Assumptions you can change
2.5%
7%
15
24c

Use the rate on your actual lease or PPA quote. There is no published statewide average we trust enough to hardcode.

2%
Estimated system: 8.7 kWAnnual usage: 13,654 kWhState credit: $0

Cash purchase

$18,879 after state credit

Year 1 benefit
$157/mo
Payback
10 years
20 year net position
$26,808

A Hollywood cash purchase leans on four quiet levers: a flat $160 city permit, no sales tax on the system, no property assessment bump, and monthly kWh credits at FPL that roll up to twelve months.

Solar loan

$264/mo 15 yr payment

Year 1 net
-$107/mo
Upfront
$0
20 year net position
-$1,748

Loan figures use Florida cost benchmarks. In the HVHZ, insist that quotes break out engineering and attachment hardware, since that is where Broward pricing diverges from inland Florida.

Lease / PPA

$0 down you buy the power

Year 1 net
-$118/mo
Upfront
$0
20 year net position
-$30,447

The 25D homeowner credit ended December 31, 2025. Judge any Hollywood lease on its escalator and on who is responsible for HVHZ engineering documents and reroof detach and reset costs.

Estimates, not quotes. Inputs use the FPL 2024 residential average from EIA, our downtown Hollywood PVGIS run, and EnergySage Florida cost data. The tool cannot model the twelve month credit cycle or the COG-1 annual true up rate. We are a solar installer and we also partner with other solar companies. See our disclosures.

We are a solar installer and we also partner with other solar companies.

Hollywood questions, sourced answers

How much is the solar permit in Hollywood?
$160 flat for a photovoltaic system permit including stationary energy storage, with no charge for the second review and $40 per 15 minutes for each review after that, per Resolution R-2025-363 adopted October 9, 2025. Fee resolution.
Why do my plans go to Broward County before the city?
Hollywood and Broward County run a joint ePermits OneStop site where applications and plans get county approvals first, then move to the city for plan review. ePermits OneStop.
Do I need both an electrician and a roofer?
Usually two licenses are involved. An EC electrical contractor pulling the permit triggers a CCC roofing sub permit for the attachment. A CVC solar contractor can lead without the roofing sub but must have an EC electrical contractor on the job. City checklist.
What wind speed is my system engineered for?
Hollywood is in the High-Velocity Hurricane Zone. Broward design speeds run 156 to 185 mph across risk categories, with a typical Risk Category II home checked at a 170 mph 3 second gust. Sealed engineering or an FSEC approval report is mandatory. FBC 1620.2.
What happens to extra power my panels send to FPL?
It becomes a kWh credit on the next month's bill, banking up to twelve months. Whatever is left when the calendar year closes gets settled at the COG-1 as available rate, which is far below retail. Rule 25-6.065.
Does going solar raise my property taxes or cost sales tax?
No on both. Solar systems and components are sales tax exempt under Statute 212.08(7)(hh), and Statute 193.624 excludes the device value from your residential assessment. Statute 193.624.

Get a Hollywood quote with the engineering priced up front

Tell us your roof age too. In this county, pairing a reroof with the array often beats paying a detach and reset two years later.

What does your monthly electric bill look like?

Hollywood average is $167 per month (EIA, 2024).